By mid 2018, the Independent Certifier identified that the works under the contract were behind schedule and over budget.
Following delivery of a Cure Plan in August 2018, VWA engaged Ontoit to lead and deliver a Project Recovery Plan and to assemble a specialist team to manage the project recovery within a constrained program.
Ontoit was engaged to lead the project recovery process. Our role entailed delivering a Project Recovery Plan and assembling a specialist team to manage the project recovery within a challenging and constrained program.
Services provided: